Free 3E551 Volume 5 URE Quiz: Master Air Force Site Planning

Think you can ace this Air Force site planning quiz? Dive in and tackle IGESP development and wartime deployment questions now!

Difficulty: Moderate
2-5mins
Learning OutcomesCheat Sheet
Paper art illustration for air force site planning igesp development wartime deployment quiz on golden yellow background

Attention 3e351 specialists! Ready to put your Air Force site planning skills to the test? Dive into our free 3E551 Volume 5 URE quiz, designed to sharpen your IGESP development test insights and challenge your wartime deployment trivia knowledge. Whether you're mastering base layouts or refining emergency management plans, this quiz serves as the ultimate Air Force site planning quiz to validate your expertise. Perfect for aspiring and seasoned planners alike, it's time to prove your prowess. Eager for more? Gear up with the 3F3X1 URE practice quiz or explore advanced scenarios in 3e6x1. Take on the challenge - start now!

What does IGESP stand for in Air Force site planning?
Integrated Ground Engineering Support Program
Installation Guidance & Engineering Support Protocol
Installation Growth & Expansion Support Plan
Installation General Engineering Support Plan
IGESP stands for Installation General Engineering Support Plan, a long-range plan for facility and utility requirements at Air Force bases. It provides the framework for programming and programming documentation. The IGESP ensures coordinated development across all engineering functions. https://www.afcec.af.mil
Which phase of Air Force site planning involves defining facility requirements and project scope?
Construction
Design Development
Schematic Design
Programming
The Programming phase establishes project needs, scope, and budget targets before any design work begins. It produces the programming criteria used in later design phases. Proper programming prevents scope creep and oversizing or undersizing facilities. https://www.wbdg.org
What is the first step in conducting a site reconnaissance for planning purposes?
Global positioning system survey
Full topographic survey
Reviewing existing maps and records
Performing soil borings
Site reconnaissance begins with reviewing existing maps, aerial photos, and records to understand site history and constraints. This background enables efficient selection of locations for detailed field surveys. It reduces costs by focusing efforts where they are most needed. https://www.epa.gov
What is the primary purpose of establishing a survey control network on a site?
To locate underground utilities
To map vegetation cover
To test soil bearing capacities
To provide fixed reference points for all subsequent surveys
A survey control network creates a series of accurately located and leveled benchmarks. These benchmarks serve as reference points for all detailed surveys, ensuring consistency. Without them, subsequent layout and grading would lack accuracy. https://www.fhwa.dot.gov
Which Air Force Instruction (AFI) provides guidance on environmental site assessments?
AFI 32-7042
AFI 36-2903
AFI 10-217
AFI 91-202
AFI 32-7042, Hazardous Material Emergency Planning and Response, also directs environmental site assessment processes. It addresses identification of potential contamination and corrective actions. Compliance ensures protection of human health and the environment. https://static.e-publishing.af.mil
What does UFC stand for when referencing Air Force facility design guidance?
Uniform Forces Communication
Utility Foundation Code
Unified Facilities Criteria
Unit Floor Configuration
UFC stands for Unified Facilities Criteria and is the governing design manual for all Department of Defense facilities. UFCs standardize requirements across services. They ensure interoperability and consistency in planning and design. https://www.wbdg.org
What is the main objective of an installation master plan?
Specify furniture layouts
Detail construction schedules
Coordinate land use, infrastructure and development over time
Establish military training zones
The master plan outlines future development of facilities, utilities, and transportation networks. It balances mission requirements with environmental and community considerations. A clear master plan helps guide programming and budgetary decisions. https://www.afcec.af.mil
Which tool is commonly used to estimate building space requirements for different functions?
Boring logs
Thermal imaging
Proctor compaction test
Planning factor tables
Planning factor tables provide standardized space allocations for various functions based on typical unit sizes. They ensure consistency and efficiency in early programming. These tables are updated as mission requirements evolve. https://wbdg.org
Which factor is critical when selecting a site for a communications tower?
Distance to nearest runway
Soil pH level
Wind load only
Line-of-sight elevation to coverage area
Line-of-sight elevation maximizes signal propagation and reduces multipath interference. Other factors like wind loading and foundation capacity are also considered after elevation. Without sufficient elevation, coverage gaps occur. https://www.fcc.gov
What is the typical backup power source for mission-critical loads on an Air Force installation?
Diesel emergency generators
Hydroelectric power
Battery-only UPS systems
Solar panels alone
Diesel emergency generators provide reliable backup power when the primary source fails. They are sized for critical loads and comply with UFC guidelines. Generators are routinely exercised to ensure readiness. https://www.afcec.af.mil
Which plan addresses alternative energy sources during wartime operations?
Environmental Site Assessment
IGESP
Installation Master Plan
Contingency Energy Plan
The Contingency Energy Plan defines energy resilience measures for wartime and contingency operations. It identifies alternate supplies and generation capacity. This ensures continuous operations under degraded conditions. https://www.ev.energy.gov
What is the recommended minimum slope away from building foundations for proper drainage?
2 percent (¼ inch per foot)
5 percent
0.5 percent
10 percent
A 2 percent slope ensures adequate water runoff away from the foundation to prevent moisture issues. Slopes less than this can allow water pooling and infiltration. This guideline is specified in UFC and ASTM standards. https://www.astm.org
Which test equipment is commonly used for measuring soil compaction during site preparation?
Anemometer
Nuclear density gauge
Seismograph
Thermocouple
A nuclear density gauge measures in-place soil density and moisture quickly. It compares results to Proctor test values for compaction quality. Proper compaction avoids settlement and structural issues. https://www.astm.org
What remote sensing method uses laser pulses to create high-resolution topographic maps?
RADAR
Photogrammetry
LiDAR
Satellite imagery
LiDAR (Light Detection and Ranging) uses laser pulses from aircraft or UAVs to measure distances and generate detailed terrain data. It penetrates vegetation for ground elevation models. LiDAR height accuracy supports precise site planning. https://www.usgs.gov
When siting fuel storage on an installation, what is the primary safety concern?
Proximity to airfield runways
Distance from ignition sources and occupied buildings
Orientation relative to wind direction
Aesthetic integration with landscape
Fuel storage must be located to minimize risk to personnel and facilities if a spill or fire occurs. Minimum separation distances from buildings and ignition sources are specified in UFC standards. Proper siting reduces potential blast and fire hazards. https://www.afcec.af.mil
How often should the IGESP be reviewed and updated to remain current?
Every 5 years
Every year
Every 10 years
Only when major changes occur
IGESPs are typically reviewed on a five-year cycle to align with funding and strategic planning updates. Regular reviews ensure the plan addresses new mission requirements and infrastructure changes. This periodic update helps maintain relevancy and supports programming. https://www.afcec.af.mil
In site planning, who is the primary stakeholder responsible for defining the scope of facility requirements?
Base civil engineer
Mission owner or affected unit
Environmental compliance officer
Contracting officer
The mission owner or affected unit defines operational needs and space requirements. Their input shapes programming criteria in the IGESP. Other stakeholders contribute technical guidance thereafter. https://www.wbdg.org
What is the minimum lateral separation required between potable water lines and sanitary sewer lines to prevent contamination?
10 feet
2 feet
5 feet
20 feet
A 10-foot horizontal separation minimizes risk from leaks or cross-connections. UFC and EPA standards specify this minimum for health protection. Reduced separation may be allowed with additional safeguards. https://www.epa.gov
When calculating heat load for a new facility, which factor must be included?
Color of exterior finish
Distance from runway
Occupant density and equipment loads
Proximity to potable water line
Heat load calculations account for internal gains from occupants and equipment plus external gains from climate. Accurate loading ensures HVAC systems are neither undersized nor oversized. Omitting occupant or equipment gains leads to temperature control issues. https://www.ashrae.org
What is the typical per-person daily water demand factor used in base planning?
500 gallons per person per day
10 gallons per person per day
250 gallons per person per day
100 gallons per person per day
A planning factor of 100 gallons per person per day covers drinking, sanitation, and operational uses. This factor supports sizing of water treatment and distribution systems. Actual usage may vary but the standard provides a baseline. https://www.wbdg.org
In contingency operations, how long must a fuel system remain operational without resupply?
24 hours
7 days
12 hours
72 hours
Contingency fuel systems are designed to sustain operations for at least 72 hours without resupply. This requirement ensures mission continuity during initial deployment phases. Logistics planning uses this threshold for fuel storage sizing. https://www.af.mil
What is the typical electrical load factor for an Air Force administrative building?
0.90
0.40
1.00
0.05
An administrative building has a load factor of about 0.40 to account for diversity in equipment usage. This factor adjusts peak demand calculations for sizing transformers and feeders. Overestimating load factor can lead to inefficient system design. https://www.ashrae.org
Which requirement governs noise contours around flight line planning?
SEL 50 dB
L10 70 dB
Lmax 80 dB
Day-night average sound level (DNL) 65 dB
A DNL of 65 decibels is the threshold for acceptable outdoor noise levels near airfields. Planning must keep sensitive uses outside this contour. FAA and DoD guidelines adopt this standard to minimize noise complaints. https://www.faa.gov
When designing pervious areas, which soil property is most critical for infiltration?
Hydraulic conductivity
Shear strength
Plasticity index
Atterberg limits
Hydraulic conductivity measures how quickly water moves through soil, critical for stormwater infiltration designs. It determines retention basin sizing and overflow controls. Accurate testing prevents flooding and erosive runoff. https://www.epa.gov
What is a key consideration when integrating renewable energy into a base's power grid?
Color of solar panels
Average soil compaction
Distance from flightline
Intermittency and storage requirements
Renewable sources like solar and wind are intermittent, so storage or backup generation is needed. Integrating these resources requires grid stability analyses. Energy management systems optimize use and minimize disruptions. https://www.energy.gov
Which measure is required to prevent fuel spills from impacting groundwater?
Single-walled piping
Surface-only liners
Secondary containment with leak detection
Elevated storage without pads
Secondary containment systems capture leaks before they reach the environment, and with leak detection alarms, they ensure early response. Double-walled tanks and sumps are common methods. They comply with EPA and UFC spill prevention standards. https://www.epa.gov
Which best management practice (BMP) is used for erosion control on construction sites?
Noise barrier walls
Silt fence installation
Air quality monitoring
Drain tile installation
Silt fences trap sediment on-site and prevent soil from washing into waterways. They are cost-effective and easy to install around disturbed areas. Proper maintenance is essential for effectiveness. https://www.epa.gov
When designing a stormwater detention pond, which recurrence interval is commonly used for sizing inlet controls?
2-year storm
25-year storm
100-year storm
10-year storm
Detention ponds often use a 10-year design storm to manage moderate runoff events and protect downstream systems. This interval balances volume requirements and construction cost. Local guidelines may adjust intervals. https://www.usace.army.mil
What level of communications redundancy is specified for command and control facilities?
Single fiber connection
Satellite only
Dual diverse routing
Wireless only
Dual diverse routing ensures that two physically separate paths connect critical communication nodes, preventing a single break from isolating the facility. This level of redundancy is mandated for command and control resilience. It minimizes operational risk. https://www.disa.mil
Which standard must emergency lighting systems comply with on Air Force installations?
IEEE 802.3
NFPA 101 Life Safety Code
ASTM D5088
ISO 27001
NFPA 101 covers requirements for means of egress illumination and emergency lighting performance. Air Force installations use this code to ensure safe evacuation during power outages. Compliance is verified during inspections. https://www.nfpa.org
A facility has a peak demand of 250 kW and a load factor of 0.6. What is its average load?
150 kW
100 kW
60 kW
250 kW
Average load is calculated by multiplying peak demand by load factor. Here, 250 kW × 0.6 equals 150 kW. This helps size distribution and backup systems. https://www.ashrae.org
When designing a retention basin for a 100-year storm, which factor increases required storage volume?
Lower soil infiltration rate
Proximity to runway
Higher mean annual temperature
Larger watershed area
Lower infiltration rates reduce water loss to ground, requiring more surface storage for the same runoff volume. Retention basins rely partly on infiltration to empty between events. Accurate soil data is crucial. https://www.usace.army.mil
Which analysis compares overhead versus underground utility installation costs over a 20-year life cycle?
Payback period only
Net present value only
Life-cycle cost analysis
Return on investment only
Life-cycle cost analysis accounts for initial installation, maintenance, repair, and replacement costs over a project's life. It provides a comprehensive comparison beyond simple upfront costs. AF guidance often requires these analyses for utility planning. https://www.wbdg.org
What minimum electromagnetic interference (EMI) shielding effectiveness is required for a secure communications facility?
20 dB attenuation
40 dB attenuation
60 dB attenuation
100 dB attenuation
Secure facilities require high EMI shielding - 100 dB or more - to block external signals and prevent leaks. This level is specified in DoD TEMPEST and UFC standards. Proper installation and verification are mandatory. https://www.dtic.mil
A fuel storage tank shows 0.25 inches of settlement over 10 years. What is the average annual settlement rate?
1 inch per year
0.025 inches per year
0.25 inches per year
2.5 inches per year
Divide total settlement (0.25 in) by number of years (10) to get 0.025 in/year. Monitoring rates helps predict future performance and plan remediation. Settlement data guide foundation design improvements. https://www.astm.org
When balancing cut and fill on a grading plan, which method ensures mass-earthwork balance?
Random sampling
Hand-calculated cross-sections
3D terrain modeling
Visual inspection
3D terrain modeling software calculates volumes between existing and proposed grades accurately. It optimizes haul distances and costs by balancing cut and fill. Manual methods are less precise and more time-consuming. https://www.autodesk.com
What is the minimum fire flow rate for a large aircraft hangar as per NFPA standards?
5,000 gallons per minute
1,000 gallons per minute
3,000 gallons per minute
500 gallons per minute
NFPA 402 and 13 require a minimum of 3,000 gpm fire flow for large aircraft hangars to extinguish potential high-skill aviation fuel fires. Water supply and hydrant capacities are designed accordingly. This standard protects high-value assets. https://www.nfpa.org
How is the grounding grid resistance minimized for an electrical substation site?
Install concrete foundation only
Increase ground rod spacing and add horizontal conductors
Reduce soil moisture
Use only vertical rods at a single point
Spreading ground rods and adding conductors increases contact area, lowering resistance. Horizontal conductors further distribute fault current and reduce potential rise. Proper soil conditioning like chemical treatment may also help. https://www.ieee.org
What tilt angle optimizes solar photovoltaic panels at 35° latitude for maximum annual yield?
35 degrees
50 degrees
23 degrees
90 degrees
Matching the tilt angle to the latitude roughly maximizes annual energy collection. At 35° latitude, a 35° tilt captures optimal sun angles over the year. Seasonal adjustments may further fine-tune yield. https://www.energy.gov
In HVAC design, which diversity factor is applied to unitary systems in office buildings?
1.00
0.50
0.85
0.25
A diversity factor of 0.85 accounts for the fact not all units operate at peak simultaneously. This reduces total installed capacity, saving costs. HVAC load calculations reference this factor in ASHRAE guidelines. https://www.ashrae.org
What maximum one-way latency is acceptable for secure video conferencing in a tactical operations center?
500 milliseconds
5 milliseconds
1 second
150 milliseconds
Latency under 150 ms ensures conversational flow without noticeable delays. Higher delays degrade real-time collaboration. Tactical networks are designed to meet this performance. https://www.disa.mil
When laying out a primary water main loop, what is the recommended maximum dead-end length to prevent stagnation?
300 feet
50 feet
1,000 feet
5 miles
Dead ends longer than 300 feet risk water quality issues like stagnation and bacterial growth. Looping mains reduces flushing requirements. UFC and AWWA standards reference this limit. https://www.awwa.org
Which seismic design category applies to critical mission systems requiring immediate occupancy after an earthquake?
Category II
Category III
Category IV
Category I
Seismic Category IV structures must remain functional after a major earthquake. This category applies to mission-critical and emergency operations buildings. UFC provides design criteria for each category. https://www.fema.gov
Which factor is most important when siting a radar facility relative to terrain?
Distance from base headquarters
Wind exposure only
Elevation and clutter-free line-of-sight
Soil compaction
Radar performance depends on clear line-of-sight and minimal terrain obstruction. Elevated sites reduce masking and increase coverage. Site surveys assess clutter, vegetation, and structures. https://www.dodmrl.com
In rapid runway repair planning, which material is specified for expedient load-bearing surfacing?
Metal matting panels
Ungraded gravel
Timber planks
Asphaltic concrete
Metal matting panels, like AM-2 matting, allow fast assembly of a durable surface for aircraft operations. They distribute loads and interlock for stability. The system is standard in expeditionary airfield design. https://www.af.mil
During contested operations, how is IGESP linked with the National Environmental Policy Act (NEPA) process?
Use categorical exclusions for rapid engineering support
NEPA compliance is deferred indefinitely
NEPA requires full EIS for all actions
NEPA is waived entirely in wartime
In contingency and wartime, many actions qualify for NEPA categorical exclusions, enabling rapid execution. IGESP planning identifies projects that fit CE criteria to streamline environmental approval. Full EIS or EA is only needed for significant impacts. https://ceq.doe.gov
What is the key consideration for rapid runway repair under fire to ensure airfield operability?
Minimum manning and material caching on-site
Permanent heavy equipment storage inside hangars
Full concrete batching plant nearby
Use of standard paving procedures
Caching repair materials and lightweight equipment on-site allows fast response under fire. Full-scale batching or heavy machinery may be unavailable during attack. Preplanned rapid repair teams use AM-2 mat and portable mixers. https://www.afcec.af.mil
In joint basing scenarios, how are utilities integrated between host and tenant commands?
Utilities are provided on a handshake basis
Host relinquishes all utility control
Tenant installs all utilities independently
Through interagency Memoranda of Understanding detailing cost-share and responsibilities
MOUs define financial, operation, and maintenance responsibilities for shared utilities. They ensure clear governance and budgeting. Joint basing requires formal agreements to avoid disputes. https://www.dau.edu
What unique infrastructure requirement is specified for an expeditionary advanced landing ground?
Rapid-deployable airfield lighting systems
Underground hangar storage
Full water treatment plant
Permanent concrete taxiways
Deployable airfield lighting like portable panel systems supports night operations without fixed electrical feeds. They are lightweight and quickly installed. This meets UTC requirements for expeditionary units. https://www.af.mil
How is a hardened communications shelter designed to withstand near-miss blast overpressure?
Glass block windows
Reinforced concrete walls and blast-rated doors
Fiberboard partitions
Standard drywall interior
Hardened shelters use thick reinforced concrete walls and specialized blast doors to resist overpressures. They maintain structural integrity under shock loads. Design follows UFC blast criteria. https://www.dtic.mil
In a contested environment, what measure ensures continued utility operation despite network cyber attacks?
Remote cloud-only monitoring
All systems on single LAN
Air-gapped control systems with manual override
Unsecured Wi-Fi connections
Air-gapping critical controls and providing manual overrides prevents remote compromise. Cyber-hardened OT networks isolate SCADA from IP threats. This protects essential services during cyber conflicts. https://www.nist.gov
0
{"name":"What does IGESP stand for in Air Force site planning?", "url":"https://www.quiz-maker.com/QPREVIEW","txt":"What does IGESP stand for in Air Force site planning?, Which phase of Air Force site planning involves defining facility requirements and project scope?, What is the first step in conducting a site reconnaissance for planning purposes?","img":"https://www.quiz-maker.com/3012/images/ogquiz.png"}

Study Outcomes

  1. Understand Air Force Site Planning Principles -

    Grasp the foundational concepts of site layout, infrastructure requirements, and environmental considerations critical to effective base development.

  2. Analyze IGESP Development Processes -

    Break down each phase of the Installations, Geotechnical, and Environmental Site Planning framework to ensure compliance and mission readiness.

  3. Apply Wartime Deployment Strategies -

    Utilize scenario-based questions to practice force projection, resource allocation, and rapid site activation under combat conditions.

  4. Evaluate Site Selection Criteria -

    Assess geographic, logistical, and security factors to determine optimal locations for temporary and permanent Air Force installations.

  5. Identify Knowledge Gaps in 3E551 Volume 5 Concepts -

    Use quiz results to pinpoint areas needing review, from technical specifications to procedural standards in your 3e351 training.

  6. Optimize Deployment Decisions Under Constraints -

    Learn to balance operational requirements, resource limits, and environmental factors when planning expeditionary site setups.

Cheat Sheet

  1. Terrain and Geotechnical Siting Criteria -

    Review slope, soil bearing capacity, and drainage when planning sites; a common mnemonic is "SOFT" for Soil, Orientation, Flood risk, and Topography to recall key factors. For example, standards from the U.S. Army Geotechnical and Structures Laboratory (ASTM D2487) guide subgrade classifications. Mastering these ensures success on your 3E551 Volume 5 URE quiz and real-world mission planning.

  2. Blast Radius and Stand-off Distance Calculations -

    The UFC 3-340-02 standard uses the formula D = K·W^(1/3) (where W is the net explosive weight and K the threat-dependent factor) to calculate safe standoff distances. Memorize the "K-cubed" trick to quickly estimate blast radii under stress. Accurate calculations are central to Air Force site planning quiz scenarios and critical for force protection in wartime.

  3. IGESP Development Phases -

    IGESP development follows five key stages: Requirements Analysis, Conceptual Design, Detailed Design, Implementation, and Sustainment - and a handy mnemonic is "Really Clever Designers Implement Sustainment." Reference Air Force Pamphlet 10-1403 for detailed guidance. Master these stages to excel on the IGESP development test.

  4. Wartime Deployment Site Selection Criteria -

    Effective wartime site selection uses the "STAIRS" mnemonic: Slope, Trafficability, Access, Infrastructure, Resources, and Security to quickly assess potential locations. For instance, raw soil reports and road-network analyses can confirm trafficability under combat loads. Understanding these criteria is essential practice for any 3e351 operator tackling wartime deployment trivia.

  5. Environmental and Regulatory Compliance -

    Compliance with NEPA, Section 404 of the Clean Water Act, and the Endangered Species Act is mandatory; follow the four-step EIS process: Notice of Intent, Draft EIS, Final EIS, and Record of Decision. Remember "NEPA FDR" (Notice, Draft, Final, Record) to sequence environmental reviews. Staying current with these regulations ensures ethical site planning and scores high on the Air Force site planning quiz.